Following the installation of new industrial catering equipment within the company’s food manufacturing facility, the existing thermal oil pipework (2No 2” Lines & 1No 2.5” Lines, Carbon Steel) had to the rerouted from the existing Boiler House.
This involved the removal of redundant sections of pipework & supports from the Oven equipment and the subsequent installation of all new pipework and supports.
Site surveys of the existing process areas were undertaken to agree a ‘new route’ which would minimise disruption and overall production downtime.
Project deliverables included:
- Stress Analysis
- Mechanical Scope of Work
- Specifications
- P&IDs (Proposals and AS Builts)
- General Arrangement Drawings (Proposals and AS Builts)
- Layout Drawings