Following the installation of new industrial catering equipment within the company’s food manufacturing facility, the existing thermal oil pipework (2No 2” Lines & 1No 2.5” Lines, Carbon Steel) had to the rerouted from the existing Boiler House.

This involved the removal of redundant sections of pipework & supports from the Oven equipment and the subsequent installation of all new pipework and supports.

Site surveys of the existing process areas were undertaken to agree a ‘new route’ which would minimise disruption and overall production downtime.

Project deliverables included:

  • Stress Analysis
  • Mechanical Scope of Work
  • Specifications
  • P&IDs (Proposals and AS Builts)
  • General Arrangement Drawings (Proposals and AS Builts)
  • Layout Drawings